EARNEST ARCHIVES

FEATURE:

ALUMNI

FACULTY/STAFF NEWS

RESEARCH

STUDENTS


RETURN TO HOME PAGES

College of Engineering and Science


 

CoES on the Cooper River Bridge

The 1546 ft. cable stayed span hangs from two diamond towers. These towers reach over 575 feet into the air and support a road deck almost 200 feet above the median high tide mark.

Charleston has long been identified by its “Cooper River Bridge” — first the two-lane John C. Grace Bridge and later the three-lane Silas N. Pearman Bridge.

Both the Grace and Pearman bridges will be dismantled once traffic rolls on the new Ravenel Bridge.

Through the years, images of these two cantilever bridges, with their intricate steel trusses, have adorned postcards, T-shirts, key chains and a myriad of souvenirs. For nearly half a century, they were the primary landmarks guests looked for when visiting South Carolina’s largest city.
Soon the Charleston skyline will evolve once more, and a new eight-lane icon will span the horizon.

The S.C. Department of Transportation (SCDOT) is building America’s longest cable-stay span to replace the existing bridges that cross the Cooper River and connect Charleston and Mount Pleasant along U.S. Highway 17. The Arthur Ravenel Jr. Bridge, named for the S.C. senator who helped secure funding, is easily the state’s biggest project with a total cost of $644 million.

The Cooper River Bridge's 1546 foot main span is suspended by 128 individual cables between the support piers. Cables are anchored on the deck level and inside of the diamond towers. A single cable is composed of many seven-wire strands twisted together. Some of the strongest cables on this bridge are formed by 90 seven-wire strands. To protect the cables from changing weather conditions they are enclosed in a high density poly-ethylene (HDPE) pipe.

Clemson connection

None of the architectural renderings of the new Ravenel Bridge features the ubiquitous Clemson Tiger Paw, but perhaps they should have. From preconstruction to ribbon cutting, College of Engineering and Science (CoES) alumni have played key roles in the project.

 

Alumnus Matt Lifsey ’90 is a surveys/utilities engineer with SCDOT. From July 1998 through fall 2000, he was project manager for the Cooper River Bridge Replacement Project. During that period, the Environmental Impact Statement (EIS) was completed, and the final environmental approval for the project was received. The main-span length of 1546 ft. was established, a major milestone. Lifsey says his most significant challenge was balancing unique issues while working within a constrained budget.

“The Cooper River Bridge Replacement Project was, by far, the largest and most challenging project I've ever managed,” says Lifsey. “It has also been one of the most rewarding experiences of my professional career.” One of his last contributions to the project was being a part of the team responsible for packaging the design-build contract documents and selection of a contractor.

The chosen contractor is Palmetto Bridge Constructors (PBC), a joint venture between Tidewater Skanska, Inc. of Norfolk, Va. and Flatiron Constructors, of Longmont, Co. Parsons, Brinckerhoff, Quade and Douglas provided design services. One of the S.C. companies that worked with Parsons Brinckerhoff is the LPA Group. LPA provides engineering, architectural, planning and environmental services for the development of airports, roads and bridges.

 

Alumnus Fred Kicklighter ’89, M ’91 is manager of roadway design for LPA. As a high school student growing up in North Charleston, Kicklighter recalls driving a school bus full of junior-varsity basketball players across the old Grace Bridge.

“The two narrow lanes made that bus seem HUGE,” recalls Kicklighter. “It felt like I was barely clearing the superstructure. I don’t know who was more scared, the students who were riding or me.” Little did he know that two decades later, he’d be involved in a project that would replace not only the old Grace Bridge but the newer Silas Pearman as well.

“This new bridge will outlive me,” says Kicklighter. “So as the years go by, it’ll always be something that I can look at and tell my grandchildren — I helped build that bridge.”

Several other Clemson alumni will be able to make that claim.

 

Wade Watson ’78 has spent his career building marine structures up and down the Southeast coast — bridges, offshore structures for the Coast Guard, docks for aircraft carriers and submarines, and large piers for the Navy. The Ravenel Bridge, however, is the largest and most complex project he’s been involved with. An employee of Tidewater Skanska Inc. ,Watson is the project manager for PBC.

“Basically we had to put together a half-billion dollar construction company in a matter of just a few months, said Watson. “We had to hire people, get everybody integrated and get a team pulling together and going in the same direction.”

Important members of that team include SCDOT employees who are also Clemson alumni.

 

Graduate Tim Henderson ’90 is the youngest of four engineers in his family, yet he’s working on the largest project any of them have ever been involved with. He’s the assistant project manager for SCDOT, the “owner” of the project and administrator of the contract.

“One big challenge on this project is the design-build nature of the contract,” says Henderson. “By integrating the design with the construction, you compress the whole time schedule.”

Quality Control
Ascertaining that the bridge components meet the state’s criteria is the job of QA-QC inspectors. SCDOT also has an oversight role in quality assurance.

 

Clemson alumnus David Wertz ’97 also the youngest of a four-engineer family, is an assistant resident engineer for the SCDOT. He grew up in Charleston and remembers, as a child, asking his dad if the Grace and Pearman bridges were the largest in the world.

“I’ve worn several hats throughout the three-and-a-half years I’ve been on the project,” says Wertz. “Currently, I am one of two assistant resident engineers on the main span, doing inspections and assuring that everything is being built according to plans and specifications.”
Another Clemson alumnus who’s making sure that everything meets specifications is Keith Ingram ’99. Ingram is a special project manager for PSI, one of the subcontractors providing quality assurance services to the SCDOT.

“The main thing we test is concrete,” says Ingram. “This bridge is designed to have a useful life of 100 years, and since most of the bridge is concrete, we take our job very seriously.”

 

Completing the SCDOT roster are two Clemson engineers who graduated together in 2002. In fact, Daniel Burton and Justin Davis had partnered on their senior capstone project and are now project engineers. One of their challenges was gaining the respect of the contractor and subcontractor personnel.

“Early on, it was painfully obvious that we were the new kids on the block,” says Davis. “It’s challenging sometimes to have to tell someone who’s older and more experienced that they haven’t met specs or design criteria. We make every effort to be tactful and consistent. People respect that.”

The two have also been involved in public relations outreach efforts, making presentations to groups in the community and conducting tours for visitors to the site.

Both Henderson and Watson point out that this project is about more than erecting a structure. It has given them the opportunity to reach out and build bridges within the community. They’ve established several initiatives that have had a positive impact on local residents. Disadvantaged and minority businesses have received an economic boost from providing building services and supplies. A job-training program has meant career development opportunities for some 100 people from the surrounding neighborhoods.

Henderson points out that the SCDOT and PBC have a genuine partnering relationship. “It’s not something we walked into,” he observes. “We built this relationship over time — its foundation is trust and communication and honesty, and it’s a partnership that has benefited the community and the state.”

“People who went to Clemson, and the faculty, staff and current students, talk a lot about the Clemson family,” observed Watson. “It’s part of the ‘Clemson experience’ on campus, but those ties remain and continue, even after graduation. We’ve sure felt it here.”

The PBC and SCDOT teams have worked well together. The project will finish a year ahead of the contract schedule. Plans are being made for opening the bridge this summer, and there’ll be plenty of Clemson alumni on hand for the celebration.


More of the Clemson SCDOT team
While this article focuses on Clemson alumni working out of the SCDOT office in Charleston, there are several others stationed at the Columbia headquarters who made significant contributions to the Cooper River Bridge Project.

Assistant state bridge design engineer Barry Bowers ’85 was part of the design review team, making sure that plans met seismic, wind and collision specifications.

Quality management engineer Jay Hawkins ’85 is a member of the quality management team, reviewing field operations and documentation for all SCDOT construction projects including the bridge.

Bridge construction engineer Charles Matthews ’68 is part of a "final acceptance team" performing weekly inspections on various portions of the project.

Quality program manager Todd Steagall ’90 oversees the SCDOT quality management team.

 

 



Earnest is published by the College of Engineering and Science at Clemson University for the alumni and friends of the College. Subscriptions are free upon request.

Send any comments/questions to: Ron Grant (email: Rong@clemson.edu)
College Relations/Marketing Director, Clemson University.

College of Engineering and Science
100C Riggs Hall · Box 340901, Clemson, South Carolina 29634-0901 -- (864) 656-5711